Wednesday, October 18, 2006

No Concrete

Around 11:30am on Wednesday October 18th 2006, Economy Paving's main site superintendent, Terrence Rearden, informed the Village/MSP that crews from both concrete subcontractor A & K slipform and the brick laying subconrtractor, Syrstone, will not be on site tomorrow. This represents a change from our previous communications about the completion of the sidewalks. When asked about the delay, crews pointed out concerns about weather were the primary reason behind the delay.

Sidewalk completion crews are now expected to return on Monday October 23rd 2006. This arrival date is also weather dependent so please check with the blog for more information.