A Lone Worker
Economy Paving superintendent Terrence Rearden could be seen on Main Street today fixing some of the installed light post footers. Plans required that all light pole bases must poke 2 inches above the sidewalk/ground surface. Mr. Rearden is correcting those that are too low by adding a layer of heavy-duty grout. This work is part of the final touch-up/corrections mentioned in current MSP communications.
3 Comments:
where and when will the inscribed bricks be installed?
Hi anonymous. I do hope that you return to the blog to get the answer to your question.
Engraved bricks will be installed next summer. They are going in areas where you can see blank bricks now. Hence, a blank brick will be swapped out for an engraved one. Nearly every brick arch on Main Street will feature a mix of blank and engraved bricks.
Originally, engraved bricks were supposed to go in this fall, but the supplier could not get the bricks to us in time. I hope this answers your question and you can always feel free to contact the project directly at 387-4471 or tburgmainst@fltg.net
great!!
It looks really good walking and driving through the village