Driveway Completions

Crews from concrete subcontractor A & K Slipform are still on site and continue to pour concrete. Teams began to pour some of the wheelchair ramps on Main Street today, which had to wait till last because of the texturing/details on each of the ramps. Crews poured one such ramp at the brick arch near the Ronogovian Embassy to the USA. Tomorrow, brick layers can place bricks around this ramp and finish up that arch. That will mean the end of all work on the southside of West Main Street.

Crews also poured the remaining sections of driveway needed by Dragon Village and Colonial Laundromat.

Economy Paving has begun its final work by having its crews fill in areas of future tree lawn with soil/gravel. These areas (the areas between the curb and sidewalk) will be planted with new landscaping come spring.