Change to Curbing Schedule
Members of the subcontractor installing new gas main pipes for NYSEG have requested that the curbing teams from Geneva Curb delay the start time for curb installation. The gas main teams believe that the gas main needs an additional 200 ft of new pipe to replace the aging main running along the south side of Main Street to Elm Street. The curbing teams only want to begin their work after all the gas main have come in (as to avoid having to dig up he brand new curbs!) and have decied to honor the gas main team's request. Hence, Geneva Curb will not begin installaing new curb tomorrow as reported in our earlier blog post today (Tuesday September 12th 2006). It now appears that new curbs will begin to go down on the north side of West Main Street (by the Post Office) either on Thursday September 14th 2006 or Friday September 15th 2006. While this dealy does slow down the installation of the curb it does not represent a major setback to the project.
0 Comments:
Post a Comment
<< Home